Amazon expects its capital spending to reach about $220 billion in 2026, a company record, with most of the money going to Amazon Web Services (AWS) and AI infrastructure. AWS finance chief John Felton said the risk of moving too slowly on AI outweighs the risk of investing heavily. That does not mean buying all the equipment up front.
In an email interview with Business Insider, Felton said AWS secures land, power and permits early because each can take years to obtain. Land and power can serve multiple uses over time. Servers, by contrast, can wait: AWS uses customers’ multiyear orders to decide how much capacity to build and buys servers only a few months before they are due to go online. If demand does not materialize, Felton said, AWS does not place the equipment order.
What AWS looks for in customer orders
Felton said customers were committing to capacity faster than AWS could install it. In the third quarter of 2026, AWS had a $578 billion order backlog, which he said was growing at a triple-digit rate. AWS revenue growth had accelerated for six consecutive quarters, reaching 39.3% in the latest quarter.
Felton described long-term orders as the first test of demand, not the sole measure of a return. AWS also tracks whether investments pay for themselves, how quickly revenue grows and whether margins hold up. He expects returns on infrastructure to accrue over years. In his view, customers that already run applications and store data on AWS have a reason to run AI workloads there too, increasing their use of computing power and storage.
The lesson from Amazon’s warehouse expansion
Felton, who spent about two decades in Amazon finance and operations roles before moving to AWS, drew a comparison with the pandemic. Amazon doubled the size of a logistics network it had taken 25 years to build, then had to put that capacity to use more efficiently. Organizing the US delivery network by region put inventory closer to customers, which Felton said reduced fulfillment costs and shortened delivery times. Where AWS places computing capacity likewise affects how well it can serve customers, he said.
Even with orders in hand, the constraint on a new data center can shift. Felton cited power, permits, chips, memory, networking equipment and optical modules: resolving one shortage can expose another. He said AWS also starts talking with local governments and residents during planning about how a proposed data center could benefit its host community.